Thursday, February 14, 2008

Quantitative Aptitude Question No.4

Quantitative Aptitude Question No.4

A contractor agreeing to finish a work in 150 days, employed 75 men each working 8 hours daily. After 90 days, only 2/7 of the work was completed. Increasing the number of men by ________ each working now for 10 hours daily, the work can be completed in time.

Answer
150 men.

Explanation
One day’s work = 2 / (7 * 90)
One hour’s work = 2 / (7 * 90 * 8)
One man’s work = 2 / (7 * 90 * 8 * 75)
The remaining work (5/7) has to be completed within 60 days, because the total number of days allotted for the project is 150 days.
So we get the equation
(2 * 10 * x * 60) / (7 * 90 * 8 * 75) = 5/7 where x is the number of men working after the 90th day.
We get x = 225
Since we have 75 men already, it is enough to add only 150 men

No comments:

2008 Placement papers of Top MNC companies

eXTReMe Tracker